How much will US data center construction spending be in October 2026?
GitHub · suggest a change · how to contribute
The number
Each month the Census Bureau estimates the value of private data center construction put in place in the US, as a seasonally adjusted annual rate.1 Buildings, site work, backup power and cooling count; racks and servers do not.2 The monthly series starts in January 2014.1
How Census estimates it
- A sample of projects. Drawn from Dodge Construction Network's lists of project starts. Projects of $100 million or more are all included.3
- Owners report monthly, voluntarily. For a project that has not reported, Census fills in its total cost times the share that similar projects had completed at the same age. In 2025, 78% of private nonresidential dollars were filled in this way.3
- Earlier months change. Filled-in values are redone each month and late reports replace them, and each release so far has revised the two months before it. A yearly revision comes each July.3,4
- Projects missing from the lists are covered by raising the total 25%.3
The question
Will the first published figure for October 2026 be above each of eleven strikes, from $90B to $115B in steps of $2.5B? Census publishes it on Dec 1, 2026, at 10:00 a.m. ET.5 Later revisions do not count.6 Rules →
Sources
- US Census Bureau. Value of Private Construction Put in Place, seasonally adjusted annual rate, monthly. Release of 2026-11-02.
- US Census Bureau. Construction Spending definitions.
- US Census Bureau. Value Put in Place methodology.
- US Census Bureau. Analysis of revisions to monthly estimates.
- US Census Bureau. Construction Spending release schedule.
- Kalshi. KXDATACENTCON market rules.
Last updated 2026-11-10 · history
Nothing here is financial advice or a recommendation to trade.